Issuance of Temporary Electrical Permit

Temporary Electrical Permits must be secured from the City Government after securing Building Permit purposely for use during the construction phase.
Office or Division Office Of The Building Official (OBO)/Office Of The City Engineer Type of Transaction G2G (Government to Government)/G2B (Government to Business)/G2C (Government to Client)
Classification Simple Who May Avail ALL
CHECKLIST OF REQUIREMENTS WHERE TO SECURE

  1. ACCOMPLISHED FORMS of TEMPORARY ELECTRICAL PERMIT. Signed and sealed by the Architect/Civil Engineer, Master Plumber/Sanitary Engineer, Professional Electrical Engineer (P.E.E.), Professional Electronics Communication Engineer (P.E.C.E.) and Professional Mechanical Engineer (P.M.E.) - five (5) sets each
  2. ACCOMPLISHED FORMS Mayors Permit, signed by the owner; three (3) sets
  3. BARANGAY CLEARANCE for Building Permit Application to be secured at the specified barangay where the construction will be done. One (1) copy
  4. TAX DECLARATION to be secured from the Assessor’s Office One (1) copy
  5. REAL PROPERTY TAX CLEARANCE to be secured from the Treasurer’s Office One (1) copy
  6. LOT PLAN WITH VICINITY MAP certified by the Geodetic Engineer. One (1) copy
  7. TRANSFER CERTIFICATE OF TITLE/DEED OF SALE and or LEASE OF CONTRACT/CONTRACT TO SELL in case the applicant is not yet the registered owner of the lot. One (1) copy
  8. RESIDENCE CERTIFICATE of the applicant (current year). One (1) copy
  9. LOCATIONAL CLEARANCE One (1) copy
  10. VALID IDENTIFICATION CARD of the applicant and lot owner/representative One (1) copy

  1. OBO



  2. OBO
  3. Barangay Hall where the construction be located

  4. Assessor’s Office
  5. Treasurer’s Office

  6. Owner’s engineer
  7. Owner


  8. Owner
  9. Zoning/City Planning & Development Office
  10. Owner