Temporary Electrical Permits must be secured from the City Government after securing Building Permit purposely for use during the construction phase.
Office or Division
Office Of The Building Official (OBO)/Office Of The City Engineer
Type of Transaction
G2G (Government to Government)/G2B (Government to Business)/G2C (Government to Client)
Classification
Simple
Who May Avail
ALL
CHECKLIST OF REQUIREMENTS
WHERE TO SECURE
ACCOMPLISHED FORMS of TEMPORARY ELECTRICAL PERMIT. Signed and sealed by the Architect/Civil Engineer, Master Plumber/Sanitary Engineer, Professional Electrical Engineer (P.E.E.), Professional Electronics Communication Engineer (P.E.C.E.) and Professional Mechanical Engineer (P.M.E.) - five (5) sets each
ACCOMPLISHED FORMS Mayors Permit, signed by the owner; three (3) sets
BARANGAY CLEARANCE for Building Permit Application to be secured at the specified barangay where the construction will be done. One (1) copy
TAX DECLARATION to be secured from the Assessor’s Office One (1) copy
REAL PROPERTY TAX CLEARANCE to be secured from the Treasurer’s Office One (1) copy
LOT PLAN WITH VICINITY MAP certified by the Geodetic Engineer. One (1) copy
TRANSFER CERTIFICATE OF TITLE/DEED OF SALE and or LEASE OF CONTRACT/CONTRACT TO SELL in case the applicant is not yet the registered owner of the lot. One (1) copy
RESIDENCE CERTIFICATE of the applicant (current year). One (1) copy
LOCATIONAL CLEARANCE One (1) copy
VALID IDENTIFICATION CARD of the applicant and lot owner/representative One (1) copy